11.  All of the following represents activities / responsibilities of a product owner, EXCEPT:

(A)      Ensuring the team has a common vision for the project
(B)      Making decisions that provide a better ROI from the project
(C)      Funding the project
(D)      Participating in the planning poker game to clarify questions
 
 

Answer C

Description

Why (C): Funding the project is done by the sponsor / client.  This is not the responsibility of a product owner (PO), since the PO could be anyone representing the client
Why NOT (A), Why NOT (B), Why NOT (C): A product owner has to be responsible for all of these actions


Reference

 Agile Estimating and Planning, Mike Cohn, chap 3