6.      In a time boxed release plan, the release date is defined in advance.  If so, what is NOT defined in this type of release plan?

(A)      Scope
(B)      Schedule
(C)      Cost
(D)      Quality
 

Answer A

Description

Why (A): In time boxing, specific features are not defined, since whatever can be accomplished in that time period will be done.  
Why NOT (B): Schedule is already defined in advance here
Why NOT (C), Why NOT (D): Whether we adopt time-boxed or scope-boxed releases, the cost and quality will not change. So this is not a parameter to consider


Reference

 The Art of Agile Development - James Shore & Shane Warden, page 212